Comparative Analysis of Time and Cost Efficiency in Project Acceleration Strategies: A Case Study of the Construction of a Police Service Building

Authors

  • Widia Dini Afrida Universitas Muara Bungo, Indonesia
  • Muhammad Sodri Renjani Universitas Muara Bungo, Indonesia
  • Devit Rahmawati Universitas Muara Bungo, Indonesia
  • Radinal Radinal Universitas Muara Bungo, Indonesia

DOI:

https://doi.org/10.59525/gej.v3i1.288

Keywords:

Cost Efficiency, Project Acceleration, Project Management, Time Cost Trade-Off

Abstract

Optimal time and cost management are fundamental factors in ensuring the success of construction projects. One effective approach to address the risk of delays and cost overruns is the Time Cost Trade-Off (TCTO) method, which allows for project duration compression through resource adjustment and cost control. This study aims to analyze and compare two acceleration scenarios for the construction of the Police Service Building in Bungo Regency: additional working hours (overtime) and additional labor. This study uses a descriptive quantitative approach through a case study. The Critical Path Method (CPM) is applied to identify the critical path as the basis for implementing the TCTO strategy. The results of this study indicate that both scenarios can accelerate the project duration from 214 days to 130 days, with a time efficiency of 39.25%. The overtime scenario provides a cost efficiency of 0.38%, while additional labor results in an efficiency of 0.16%. Although overtime is more economical in nominal terms, the additional labor strategy is considered more stable and feasible to implement in public projects with sufficient work space. The results of this study contribute to strategic decision-making in data-driven construction project management.

References

Biswas, S.K., Karmaker, C.L., dan Biswas, T.K., 2016. Time-Cost Trade-Off Analysis in a Construction Project Problem: Case Study. International Journal of Computational Engineering Research, (November 2017), 2250–3005.

Eka Shodiq Permadi, Hanie Teki Tjendani, dan Budi Witjaksana, 2025. Optimizing Time Calculation with Extended Working Hours in the Periodic Road Maintenance Project on Jl. Ir. Soekarno Ruas 3, Blitar City. International Journal of Mechanical, Industrial and Control Systems Engineering, 2 (1), 09–19.

Ernst, E., Merola, R., & Samaan, D. (2019). Economics of artificial intelligence: Implications for the future of work. IZA Journal of Labor Policy, 9(1), 1-35.

Galagali, A.A., 2017. Time-Cost-Quality Trade-off in Construction Project Management. International Journal of Civil Engineering, 4 (8), 24–31.

Hegazy, T., 2002. University of Waterloo. The Grants Register 2025, (January 2002), 1316–1317.

Laksana, B.I., 2020. Aplikasi Metode Time Cost Trade Off Untuk Mengoptimalkan Waktu Dan Biaya Pekerjaan Proyek Pada Pembangunan Gedung Pengairan Universitas Brawijaya. Journal of Civil Engineering and Planning, 1 (1), 1–79.

Luthan, P.L.A., Sitanggang, N., Alvan, S., dan Prayogo, W., 2024. Analysing the Causes of Management and Production Delays in the Implementation of Construction Project Work. Journal of Applied Engineering and Technological Science, 5 (2), 1221–1231.

Project Management Institute, 2017. PMBOK® Guide Sixth Edition (PMI, 2017). Project Management Institute.

Purnomo, D., Oetomo, W., dan Marleno, R., 2024. Analysis of Project Delay Using the Critical Path Method (Cpm): a Case Study on the Construction Project of the Opd Office Building in Pasuruan. Journal of Humanities Social Sciences and Business (Jhssb), 3 (2), 498–508.

Radinal, R., Putra, M.R., dan Wijaya, S., 2022. Perbandingan Biaya dan Waktu Pekerjaan Pelapis Dinding Luar antara Konvensional dan Alumunium Composite Panel (ACP) (Studi Kasus: Pembangunan Gedung Universitas Muara Bungo). Jurnal Civronlit Unbari, 7 (2), 70.

Rahman, I.A., Al Ameri, A.E.S., Memon, A.H., Al-Emad, N., dan Alhammadi, A.S.A.M., 2022. Structural Relationship of Causes and Effects of Construction Changes: Case of UAE Construction. Sustainability (Switzerland), 14 (2).

Sarwani, Baihaqi, I., dan Utomo, C., 2024. Causes of Delay in EPC Projects: The Case of Indonesia. International Journal on Advanced Science, Engineering and Information Technology, 14 (2), 618–628.

Sofia, D.A. dan Putri, A.A.E., 2021. Analisis Perbandingan Penambahan Jam Kerja dan Tenaga Kerja terhadap Waktu dan Biaya Proyek dengan Metode Time Cost Trade Off. Industrial Research Workshop and National Seminar, 12, 846–854.

Sutrisno, W.T., Beatrix, M., dan Fatmawati, L.E., 2024. Analisis Percepatan Waktu dan Biaya pada Proyek Pembangunan Gedung Sekolah Dasar Wachid Hasyim Kota Surabaya Menggunakan Metode Crashing. Portal: Jurnal Teknik Sipil, 16 (1), 123.

Underdahl, L., Ditri, M., & Duthely, L. M. (2024). Physician burnout: evidence-based roadmaps to prioritizing and supporting personal wellbeing. Journal of healthcare leadership, 15-27.

Downloads

Published

2025-08-20

How to Cite

Afrida, W. D. ., Renjani, M. S. ., Rahmawati, D. ., & Radinal, R. (2025). Comparative Analysis of Time and Cost Efficiency in Project Acceleration Strategies: A Case Study of the Construction of a Police Service Building. Global Education Journal, 3(1), 211–217. https://doi.org/10.59525/gej.v3i1.288